HOME  INFORMATIONAL POSTINGS      CAREERS    SITE MAP CONTACT US   
                                                           
Javascript DHTML Drop Down Menu Powered by dhtml-menu-builder.com
  Liquefaction Project  
 
       
  Liquefaction Project  
  The Project  
  Liquefaction Project Benefits  
  LNG Export Project Video  
  Project Status  
  Liquefaction FAQs  
  Open House Meetings  
  PROJECT STATUS
 

Liquefaction Project Status and Schedule

 

In 2010, Freeport LNG engaged CH•IV International to work on a pre-FEED study and alternative liquefaction technology evaluation.  As a result of that analysis, Freeport LNG selected Air Products and Chemicals, Inc. (APCI) as the technology provider for their experience and overall performance of their proprietary cryogenic liquefaction process. Freeport LNG also selected Chicago Bridge and Iron (CB&I) and Zachry to complete the engineering and design work necessary to submit an application to the Federal Energy Regulatory Commission by August 2012.

   
  In January 2012, the CB&I/Zachry joint venture was awarded a front-end engineering and design (FEED) contract to design the project's three liquefaction trains and the corresponding pretreatment facilities.
   
 

The liquefaction project is expected to take two to three years for engineering and permitting, and four to five years for construction. Freeport LNG filed its formal FERC application pursuant to Section 3 of the NGA in August 2012 and anticipates receiving FERC’s authorization to commence construction by the third quarter of 2013.  By that time the project is also expected to have received authorization from the Department of Energy to export LNG to non-Free Trade Agreement (FTA) countries. A construction schedule of approximately four to five years to completion and start-up of the liquefaction project is then envisaged in 2017.

   
 
Key Milestone Activities Date/Anticipated Date
Commencement of Front End Engineering Design (FEED) December 2010
Request to FERC to Initiate Pre-filing Review Process December 2010
Application to DOE for Long-Term Authorization to Export LNG to non-FTA countries December 2010 & 2011
Filing of formal NGA Section 3 Application to FERC August 2012
Issuance by FERC of Environmental Assessment/Environmental Impact Statement July 2013
DOE’s Issuance of Authorization to Export LNG to non-FTA Countries Early 2013
FERC’s Issuance of Authorization to Construct and Operate 3Q 2013
Commencement of Construction 3Q 2013
Liquefaction Project In-Service Date 2017